In all the opinions proposed on road access up Lynn Canal, there is one possibility that has been glossed over and another not even mentioned, or at least I haven’t seen it. (more…)

Juneau Road project moves into new realm

Monday, July 20th, 2009

50-mile road designated a ‘mega-project’; cost estimate from highway agency at $491 million
By Pat Forgey | JUNEAU EMPIRE

New cost estimates boosting the Juneau Access Project to half a billion dollars has moved the road into the realm of “mega-projects,” a designation bringing with it new federal regulations.

A Federal Highway analysis of the 50.8 mile road up the east side of Lynn Canal is estimated to cost $491 million to complete, according to a Federal Highway Administration agency. So far $25 million has been spent. (more…)

Juneau road project to cost nearly half a billion

Friday, July 10th, 2009

Alaska Channel 2 News staff
Thursday, July 9, 2009

ANCHORAGE, Alaska — The Juneau road project will cost the state nearly half a billion dollars. (more…)